Widening activity in Staunton
Virginia continues efforts to transform the Interstate 81 corridor with a comprehensive new study. The Virginia Department of Transportation (VDOT), working alongside the Office of Intermodal Planning and Investment and the Department of Rail and Public Transportation, is developing an updated Corridor Improvement Plan (CIP) for the entire 325-mile I-81 corridor within the Commonwealth. This latest initiative builds upon the success of the previous 2018 study, which identified 65 construction projects worth approximately $3 billion that are already completed or are now in development.
Current and Upcoming Projects in Our Region
The Staunton Construction District has two active projects and three more on the horizon:
Currently Underway:
- Widening to three lanes between Exit 221 and Exit 225 in both directions through the City of Staunton (completion projected for June 2027)
- Adding a truck climbing lane near Weyers Cave between mile markers 234 and 237 Southbound (completion projected for December 2027)
Planned Projects:
- Widening to three lanes between Exit 243 and 247 in both directions through Harrisonburg (anticipated start September 2025)
- Extending the acceleration/deceleration lane on the Southbound side of the Mt. Sidney rest area in Augusta County (anticipated start January 2028)
- Widening to three lanes in Rockbridge County between Exit 205 and 200 Southbound (anticipated start May 2028)
With these planned improvements in progress, VDOT is reassessing traffic conditions to determine which areas require attention next, focusing on segments with the highest rate and severity of crashes or the most significant traffic delays while excluding portions where recent widenings or truck-climbing lanes have been completed or are currently under development.
Through a three-phase public engagement process, VDOT will gather community input throughout the planning process. The initial spring phase focused on issue identification through virtual surveys and interactive mapping, allowing the public to report safety and congestion problems. During the summer phase, completed in July 2025, the study team presented potential solutions at four in-person meetings held in Weyers Cave, Winchester, Bristol, and Salem, with nearly 1,700 people responding to the accompanying online survey. You can view the presentation and project boards that were shared at these public meetings at the following links:
Proposed Projects in the Staunton District
I-81 CIP Round 2 – Potential Solutions Presentation
The final engagement phase this fall will help refine recommendations before presenting them to the I-81 Advisory Committee and Commonwealth Transportation Board by year’s end.
Community input remains crucial to the success of these transportation improvements, which focus on enhancing safety, reducing congestion, and supporting economic growth along this vital corridor that serves as a critical artery for freight movement and regional connectivity.
Learn more about the 2025 Corridor Improvement Plan Study, projects previously completed and those underway at www.Improve81.org.